The 30-week project, completed in 28 weeks including additional works added, consisting of the removal and replacement of the main school plantroom and heating infrastructure to all 6 school buildings on the campus. The works were completed in a challenging live environment, with heating maintained to all occupied areas including classrooms, offices, corridors, communal areas, hall, gym throughout the winter.
The replacement with new services included the following.
- Building management systems
- Heating plant and equipment
- Flues
- Heat emitters
- Heating pipework services
- Insulation
- Water treatment
- HVAC Commissioning
- Building works, decoration and fire stopping
- Joinery works